Mumbai: Around eight kilometres of pending work on the 592-kilometre Mumbai-Goa highway is holding up a project that has been under construction for nearly two decades, with cost overruns of more than Rs 2,000 crore in the final stretch and a new completion target of April 2027, an investigation by The Indian Express has found.
The highway, National Highway 66, is 99 per cent complete overall, but around eight kilometres across five stretches in Maharashtra remain unfinished, with the pending sections between 89 per cent and 98.5 per cent done. The Maharashtra section of the highway runs for 472 kilometres and is divided into 13 packages, of which five still have work outstanding.
The pending work covers three kilometres of two bypasses, a 192-metre bridge, a 1.8-kilometre flyover, hill cutting at four locations over 1.5 kilometres, and other ongoing road work.
The 120-kilometre Goa section of the project, from the Maharashtra border to Panaji, is complete, which means that once the pending eight kilometres on the Maharashtra side are finished, the highway will finally link the two state capitals by a modern four-lane road.
For travellers between Mumbai and Goa, and for the towns and villages of the Konkan coast that lie along the route, that connection has been promised for so long that its continued absence has become a symbol of the difficulties of building infrastructure in India.
The investigation traces the delays to a set of contractors and companies whose troubles have repeatedly stalled the work.
A joint venture involving a company run by a former Congress minister of Rajasthan, a firm that featured in the Reserve Bank of India's list of defaulters, a company owned by a businessman probed by the Enforcement Directorate, and a venture headed by a former bureaucrat who led the showpiece Samruddhi Expressway project in Maharashtra are among the heavyweights linked to the five delayed stretches.
The reasons for the continuing delays range from cash flow issues and loan defaults to problems over land acquisition and local protests, officials and contractors said.
One of the delayed stretches illustrates the pattern. A consortium including Supreme Infrastructure, which was on the Reserve Bank's list of the top 100 bank defaulters in 2019, had its contract terminated after it ran into financial trouble, and the balance work was re-awarded to a firm owned by J M Mhatre, a businessman under probe by the Enforcement Directorate.
The change of contractor, the re-tendering and the fresh mobilisation of men and machinery all added years to a project that was already far behind schedule.
The cost of the delays has been steep. The overall cost estimate for the Maharashtra section has ballooned by around 44 per cent, from Rs 12,532 crore to more than Rs 18,100 crore. The overrun was primarily because of land acquisition, changes in the scope of work due to site constraints, and the construction of additional underpasses following demands from local residents, officials of the Ministry of Road Transport and Highways said.
V Umashankar, Secretary of the ministry, told The Indian Express that a lot of work had been done on the stalled stretches in the last two years and that 99 per cent of the highway was through. "All pending work will be completed by April next year," he said.
Union Minister of Road Transport and Highways Nitin Gadkari, who has championed the project, has himself expressed embarrassment at the delay. On September 9, speaking at the opening of a 5.15-kilometre corridor in Goa's Porvorim, he said he was ashamed for the delay that had happened and would skip the inauguration of the highway, which is expected next year.
The remark was widely noted because Gadkari is known for his ambitious targets for road building, and his admission underlined how far this particular project has fallen short of them.
The highway was planned in 2006 and construction began in 2007, which means the project has been underway for nearly 20 years. In that time, the road has been widened, realigned and rebuilt in stages, and much of it is now a modern highway carrying heavy traffic between Mumbai and the Konkan coast.
But the missing eight kilometres mean that the full benefit of the investment cannot yet be realised, and travellers continue to face bottlenecks, diversions and congestion on the incomplete stretches, particularly during the monsoon and the festival season, when traffic on the route surges.
The Mumbai-Goa highway is more than a link between two cities. It is the lifeline of the Konkan region, running through Raigad, Ratnagiri and Sindhudurg districts and connecting the coastal towns, ports, orchards and tourist destinations of western Maharashtra with Mumbai and Goa. For the people of the region, the highway carries their produce to market, their children to school and college, and their families to work in the cities.
Its condition affects daily life in a way that a distant expressway does not, and its incompleteness is felt as a daily inconvenience rather than an abstract failure.
The route is also vulnerable to the geography it passes through. The highway runs along the foothills of the Western Ghats, where heavy monsoon rain can trigger landslides, and sections of the road have been closed by falling earth and boulders.
In June 2024, the Goa-bound carriageway near Nandgaon village in Mahad taluka of Raigad district was shut for more than 12 hours after a landslide brought loose earth and boulders onto the road, and traffic was diverted to the Mumbai-bound carriageway until the debris was cleared. The episode was a reminder that building and maintaining a highway through this terrain requires constant attention, and that the unfinished stretches are not the only challenge the road faces.
The investigation's findings raise broader questions about how large infrastructure projects are awarded and monitored in India. The involvement of firms with histories of loan default and regulatory investigation in critical stretches of a national highway has prompted questions about the due diligence carried out before contracts are awarded, and about the mechanisms for replacing a contractor that fails to deliver.
The ministry has pointed to the progress of the last two years as evidence that the project is now on track, but the history of missed deadlines means the April 2027 target will be judged against a long record of promises.
For the contractors, the difficulties are also real. Land acquisition in the Konkan region has been slow and contested, with local residents raising demands for underpasses, compensation and changes in alignment. Cash flow problems have affected firms that took on the work at prices that later proved unviable, and the re-awarding of terminated contracts has added further delay.
These are familiar problems in Indian road building, and the Mumbai-Goa highway has suffered from most of them at one time or another.
The completion of the highway, when it comes, will transform travel between Mumbai and Goa, cutting journey times and improving safety on a route that has long been notorious for accidents. The Goa section is ready, the Maharashtra section is almost ready, and the ministry's assurance is that the last eight kilometres will be finished by April 2027.
For the people who use the road every day, the test of that assurance will be simple: whether, by next summer, the highway finally runs without interruption from Mumbai to Panaji, and whether a project that began in 2007 can at last be declared complete.
(Reporting based on The Indian Express.)