India's first high-speed rail service will commence in the last quarter of 2027, with the first section to open running from Surat to Vapi in Gujarat, Railway Minister Ashwini Vaishnaw said on Friday. The announcement, made in a post on the publishing platform Substack, gives the clearest timeline yet for the country's long-awaited bullet train, and confirms that the full Mumbai-Ahmedabad corridor will follow in phases after the opening stretch begins operations.
The first service will run on the Mumbai-Ahmedabad High-Speed Rail corridor, a 508-kilometre line that has been under construction for five years. Vaishnaw said track trials of India's indigenous B28 bullet train trainset are expected by mid-2027, with the train being manufactured jointly by the Integral Coach Factory and Bharat Earth Movers Limited, the public sector engineering company.
The B28 is designed for a top speed of 280 kilometres per hour, with a planned operational speed of 249 kilometres per hour.
The minister said the first body frame of the B28 is complete and is undergoing structural testing. He also revealed that a faster trainset, the B35, designed for 350 kilometres per hour, is the next step in India's high-speed rail programme. The B28 itself is about 202 metres long and comprises eight coaches, four motor cars and four trailer cars, carrying approximately 557 passengers, including dedicated space for two Divyangjan, or persons with reduced mobility.
It will run on a 25 kV, 50 Hz single-phase alternating current traction system.
Bharat Earth Movers Limited is manufacturing the first two indigenous trainsets at its facility in Bengaluru, Karnataka, combining indigenous engineering with advanced technology, passenger comfort and safety features. Each coach costs about 27.86 crore rupees, and the total contract value is 866.87 crore rupees, including design costs, one-time development costs and the cost of jigs, fixtures, tooling and testing facilities.
The first train is likely to be ready in the first quarter of 2027, with trial runs on the roughly 97 to 100 kilometre Surat-Vapi section targeted for May to June 2027.
Vaishnaw gave a detailed account of the pace of construction along the corridor. As of September, 456 kilometres of pier work and 371 kilometres of viaduct construction have been completed. Six lakh noise barriers have been installed along a 299-kilometre stretch, and 9,300 overhead electrification masts have been installed across a 206-kilometre viaduct.
Four mountain tunnels have been excavated, and five kilometres of the 21-kilometre tunnel in Maharashtra have been excavated using the mountain tunnelling method.
Civil work has been completed at eight stations, where architectural finishing work is now under way, and work is in progress at all three rolling stock depots at Sabarmati, Surat and Thane. The minister emphasised that the fixed infrastructure is being indigenised as well, with all major transformers of the high-speed electrification system, the cross arms on the masts, and the ground protection and feeder wires being manufactured in India.
One of the most remarkable engineering features of the project is its undersea tunnel. In Maharashtra, the corridor runs through a 21-kilometre tunnel, of which seven kilometres pass under the sea, beneath Thane Creek. This is India's first undersea rail tunnel.
Two tunnel boring machines were launched in July 2026, from Vikhroli and Sawli, and Vaishnaw described them as among the largest machines ever deployed in India. Each has a cutterhead 13.6 metres in diameter, as tall as a four-storey building, weighs over 3,000 tonnes, roughly the weight of 500 Asian elephants, and is 96 metres long, nearly five cricket pitches laid end to end.
The minister also addressed the delay of almost a decade since the project was first announced in 2017. He said the project could not start in Maharashtra for close to two and a half years because state permissions and land acquisition were pending, and then the Covid-19 pandemic took away two more years. Full construction began in earnest in 2021.
When critics ask where the bullet train is, Vaishnaw said, the honest answer is that serious construction is just five years old, and the progress made in that time speaks for itself.
Earlier statements from the Railway Ministry had pointed to commercial services on the Surat-Vapi stretch beginning in August 2027, and the full Gujarat section of the corridor being completed by December 2027, with the entire 508-kilometre Mumbai-Ahmedabad corridor targeted for completion by December 2030.
The minister's latest statement, placing the first service in the last quarter of 2027, reflects the phased approach now being taken, with the Surat-Vapi section opening first and the rest of the corridor following.
The bullet train project is one of India's most ambitious infrastructure undertakings, and the first service will mark the country's entry into high-speed rail, a technology long established in Japan, China and Europe. For passengers in Gujarat, the Surat-Vapi section will cut journey times dramatically once it opens, and for Indian Railways it will demonstrate a domestically built trainset running on domestically built infrastructure.
With trials due in mid-2027 and the first commercial service now promised before the end of that year, the project is approaching the moment when years of construction finally become a train that people can board.
The B28 has been designed with Indian passengers and operating conditions in mind, combining locally developed engineering with features aimed at comfort and safety. Reports on the trainset describe modern interiors, onboard Wi-Fi and seating for around 557 passengers across its eight coaches, with the option to add another eight coaches later if demand grows.
The train's design speed of 280 kilometres per hour will be tested on the Surat-Vapi section, while its planned operational speed of 249 kilometres per hour will make it by far the fastest train ever to run on Indian tracks.
Beyond the two prototype trainsets now being built, the Railway Ministry has placed a 5,400-crore-rupee order with BEML for the wider Mumbai-Ahmedabad bullet train fleet and future high-speed routes, signalling that the Surat-Vapi opening is intended as the beginning of a national high-speed network rather than a one-off showcase.
(Reporting based on Deccan Herald, NDTV, The Economic Times and The Indian Express.)