News / India / Maharashtra Halts Adani's 1,500 MW Tarali Hydropower Project Over Missing Wildlife Clearance
Trending India Live Updates TMNN Exclusive Latest News

Maharashtra Halts Adani's 1,500 MW Tarali Hydropower Project Over Missing Wildlife Clearance

Top Stories

Swipe or hover to pause
India

Silicon to Systems: Inside India’s ₹1.28 Lakh Crore Semicon 2.0 Push as Global Tech Giants Bet Big on Domestic Chipmaking

India

Guarding the Heartland: How India’s 51st Doppler Weather Radar in Sambalpur Strengthens Disaster Resilience under Mission Mausam

India

Connecting the Hinterland: 21 States Join Civil Aviation Ministry in ₹28,840 Crore Overhaul of Regional Flight Connectivity

India

Reimagining Global Governance: Why India’s Co-Sponsorship of the Partners for Multilateralism Coalition Marks a Diplomatic Milestone at UNGA 2026

India

Dominance in the Continental Arena: How the Indian Women's Cricket Team Clinched Gold with a Record 147-Run Victory at the Asian Games 2026

India

Countdown to the Ballot: High-Stakes Campaigning Intensifies as Haryana and Jammu & Kashmir Head into Decisive Assembly Election Final Phases

India

End of an Era in Hindi Cinema: Veteran Actor Mushtaq Khan Passes Away at 75, Industry and Millions of Fans Pay Tearful Tributes to Beloved Character Legend

India

Hire Your Vakeel: India’s Most Trusted Legal Consultation Platform to Find Top Verified Advocates Online

India

Silicon to Systems: Inside India’s ₹1.28 Lakh Crore Semicon 2.0 Push as Global Tech Giants Bet Big on Domestic Chipmaking

India

Guarding the Heartland: How India’s 51st Doppler Weather Radar in Sambalpur Strengthens Disaster Resilience under Mission Mausam

India

Connecting the Hinterland: 21 States Join Civil Aviation Ministry in ₹28,840 Crore Overhaul of Regional Flight Connectivity

India

Reimagining Global Governance: Why India’s Co-Sponsorship of the Partners for Multilateralism Coalition Marks a Diplomatic Milestone at UNGA 2026

Maharashtra Halts Adani's 1,500 MW Tarali Hydropower Project Over Missing Wildlife Clearance

The Maharashtra Forest Department has ordered an immediate halt to construction work on Adani Green Energy's 1,500-megawatt Tarali pumped storage hydropower project in Satara district, after finding that work had begun without mandatory approval from the National Board for Wildlife.

Advertisement
Advertisement

The stop-work order, issued on November 13, came hours after an investigation by The Indian Express revealed that the company had sought to revise the project's estimated cost sharply downward, from Rs 5,675 crore to Rs 56.75 crore, a cut of 99 per cent that would have slashed its statutory contribution towards wildlife conservation in the Sahyadri Tiger Reserve from Rs 227 crore to about Rs 2.27 crore.

The department's action concerns the Tarali Pumped Storage Project in Patan taluka, which falls within the deemed eco-sensitive zone of the Sahyadri Tiger Reserve, a protected landscape in the Western Ghats that is home to tigers, leopards and a host of endangered species. The 1,500-megawatt project is proposed on the Tarali dam reservoir and covers about 150.74 hectares of non-forest land across the villages of Nivade, Tondoshi, Kalambe and Jalu.

Show-cause notices were issued by Amol Satpute, Deputy Conservator of Forests in Satara, and R S Nalawade, the Range Forest Officer for Patan, to the project's manager and an authorised representative of the company.

The notices said an inspection had found that the company had commenced actual execution of the project without obtaining the mandatory prior approval of the National Board for Wildlife, given that the area falls in the deemed eco-sensitive zone of the Sahyadri Tiger Reserve.

"This matter is extremely serious and violates the provisions of the prevailing Forest and Wildlife Acts," the notices said. The forest department directed that all construction activities at the site be suspended until the necessary approvals are obtained from the competent authorities, including the National Board for Wildlife.

It also sought a detailed written explanation within three days on why construction had begun without clearance, along with all statutory clearance documents, project maps and original or attested copies of permissions for cutting trees at the site. The department warned of strict legal and punitive action under the forest laws if a satisfactory explanation and the required documents were not produced within the stipulated period.

When The Indian Express visited the site, work on the project was underway, with construction activity spread across a large area.

The controversy has two strands, and both have now drawn the attention of the Centre. The first is the missing wildlife clearance. The second is the dramatic revision of the project's cost, and the effect that revision has on the money the company must pay towards conservation.

Under the conditions set by the State Board for Wildlife, the company is required to deposit four per cent of the project cost towards conservation and protection activities at the Sahyadri Tiger Reserve. On the original estimate of Rs 5,675 crore recorded in the environmental clearance issued in February 2025, that deposit would be Rs 227 crore. On the revised figure of Rs 56.75 crore, it falls to Rs 2.27 crore.

The sequence of events, as reported, is as follows. The Union environment ministry issued environmental clearance for the project on February 11, 2025, recording the project cost at Rs 5,675 crore. The Maharashtra Pollution Control Board issued the consent to establish on April 7, 2025, allowing work to begin.

In March 2026, Maharashtra's Principal Chief Conservator of Forest (Wildlife) and Chief Wildlife Warden, M Srinivas Reddy, wrote to the company asking it to deposit Rs 227 crore and submit an affidavit confirming it would fulfil 14 other conditions, after which the proposal would go to the National Board for Wildlife.

Then, on September 8, 2026, the company submitted a notarised affidavit seeking to revise the project cost estimate to Rs 56.75 crore, exactly one-hundredth of the earlier figure. On October 12, Reddy informed the company that the revised cost had been accepted and asked it to deposit one per cent, or Rs 56.75 lakh, immediately, and to pay the remaining three per cent, Rs 1.7075 crore, after the National Board for Wildlife cleared the project.

The company deposited Rs 56.75 lakh into the bank account of the Sahyadri Tiger Reserve.

Watch Maharashtra Halts Adani's 1,500 MW Tarali Hydropower Project Over Missing Wildlife Clearance
Watch on YouTube

On October 30, Rohan Bhate, the honorary wildlife warden of Satara district, registered a complaint with the Prime Minister's grievance redressal portal and the Maharashtra government's Aaple Sarkar portal, alleging that the project cost had been stated incorrectly. On November 6, the Union environment ministry directed the state forest department to investigate the matter on priority. A week later, the forest department's inspection led to the stop-work order.

Bhate told The Indian Express that work on the project had been going on openly for many months across a huge area. "Tarali PSP work is going on openly for many months in a huge area. And the forest department has now realised that the project work was on without NBWL's approval," he said.

The company, in a statement on Monday, defended its position. It said no component of the Tarali Pumped Storage Project falls within any notified protected area and no forest land is involved, noting that a no-objection certificate confirming this was received on January 23, 2024.

It said the project had obtained environmental clearance on February 11, 2025, and that the consent to establish was issued on April 7, 2025, with construction activities commencing only after obtaining the requisite approvals from the authorities concerned.

"In parallel, the wildlife clearance process has also been duly initiated and pursued as part of EC compliance process. The proposal for Survey and Investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife. Pursuant to which the company has also submitted the proposal for clearance to the National Board for Wildlife for the total project cost and it is under consideration by the wildlife authorities. The project is being developed in full compliance with applicable statutory requirements and the directions of the competent authorities," the company said.

The company has also said the project is entirely on private, non-forest land, 3.2 kilometres from the Koyna Wildlife Sanctuary. The forest department's position, however, is that the site falls in the deemed eco-sensitive zone of the reserve, which triggers the requirement of prior clearance from the National Board for Wildlife before any work can begin.

The dispute matters beyond the fate of a single project. Pumped storage plants, which store energy by pumping water uphill to a reservoir and releasing it to generate electricity when demand is high, are a central part of India's plan to balance its fast-growing renewable energy capacity. The country is building such projects across the Western Ghats and other hilly regions, and each one must navigate the same tangle of environmental, forest and wildlife approvals.

The Sahyadri Tiger Reserve, formed by merging the Koyna Wildlife Sanctuary and the Chandoli National Park, is one of the most sensitive landscapes in Maharashtra. It is a tiger reserve under Project Tiger, and it sits within the Western Ghats, a UNESCO World Heritage site and one of the world's eight hottest biodiversity hotspots.

The four per cent deposit rule exists precisely because large projects in and around such reserves are expected to pay for the conservation work their presence makes necessary.

The question now is what happens next. The forest department's order will remain in force until the necessary approvals are obtained, while the investigation into the cost revision and the conservation obligations continues. The company has three days from receipt of the notices to explain itself and produce its documents. The Centre's priority probe adds a further layer of scrutiny to how the state handled the revised estimate.

For the state government, the episode is uncomfortable. A senior forest official first demanded Rs 227 crore, then accepted Rs 56.75 crore as the project's cost and allowed a deposit of Rs 56.75 lakh, before the department as a whole concluded that the project should not have started at all without the wildlife board's approval.

The sequence raises questions about coordination between the forest department's own wings, and about how a hundredfold reduction in a project's stated cost could be accepted on the basis of an affidavit.

For Adani Green Energy, the halt is a setback to a project that is part of its large renewable energy portfolio, though the company maintains that it has acted in full compliance with the law. The coming days will show whether the National Board for Wildlife clears the project, whether the cost question is reopened, and whether the stop-work order becomes a prolonged pause or a brief interruption.

What is already clear is that the Tarali project has become a test case for how India balances two competing priorities: the urgent need for energy storage to support its clean-energy transition, and the protection of the fragile ecosystems in which many of those storage projects must be built.

(Reporting based on The Indian Express and The Times of India.)