New Delhi: The Supreme Court on Friday dismissed two applications filed by the Tamil Nadu government seeking a direction to Karnataka to release an additional 11 thousand million cubic feet (TMC) of Cauvery river water, bringing a temporary close to the latest round of litigation in one of India's oldest and most bitter inter-state water disputes.
A bench of Justices Vikram Nath and Aparesh Kumar Singh passed the order, declining to entertain Tamil Nadu's demand that Karnataka be directed to clear a backlog the state said had built up in its share of Cauvery water. The court had reserved its order on the two applications on October 12, and pronounced its decision on Friday, November 20.
Tamil Nadu had approached the top court seeking implementation of directions issued by the Cauvery Water Management Authority (CWMA), the statutory body that oversees the sharing of the river's waters between the riparian states. The state alleged that Karnataka had not released its stipulated share, and that the shortfall was threatening farming and crops in the Cauvery delta districts.
According to the state's submissions, there was a shortfall of 11.719 thousand million cubic feet in the flows due to Tamil Nadu at Billigundulu, the inter-state border measuring point on the river, up to October 6. Tamil Nadu had asked the court to direct Karnataka to ensure that the backlog of 11 TMC of water, as it stood on October 7, was cleared immediately, and to release the water at the rate of 1.3 TMC per day over 10 days at Billigundulu.
In August, the state had alleged that it did not receive its allocated share of water despite facing a rain-deficient year. It submitted before the court that because of the shortfall of about 11 TMC, it was unable to supply any water for irrigation in large parts of the delta, where farmers depend on Cauvery water for the samba paddy season.
Karnataka, however, denied the allegations. The state told the court that it was complying with the orders of the Cauvery Water Management Authority and that it would be difficult to meet Tamil Nadu's demand for the release of an additional 11 TMC because this had been a rain-deficit year and several areas in the state had been declared drought-affected.
Karnataka argued that its own reservoirs were under stress and that releasing the extra water would put its drinking water and irrigation needs at risk.
Before pronouncing the order, Justice Vikram Nath noted that Tamil Nadu had filed a third application on Friday to bring certain additional documents on record, and orally observed that the application too would be dismissed. The court's refusal to entertain the pleas means that no additional release of water beyond what the existing mechanism provides has been ordered.
The Cauvery water dispute is one of India's longest-running inter-state river water conflicts, primarily involving Karnataka and Tamil Nadu, with Kerala and Puducherry also stakeholders in the river basin. The river originates in the Western Ghats in Karnataka, flows through Tamil Nadu, and empties into the Bay of Bengal.
For more than a century, the two states have quarrelled over how its waters should be shared, with the dispute turning particularly sharp in years when the south-west monsoon fails.
The modern phase of the dispute was settled, in part, by a judgment of the Supreme Court in February 2018, which laid down a final allocation of the river's waters. Under that verdict, Karnataka was allocated 284.75 TMC of water, Tamil Nadu 404.25 TMC, Kerala 30 TMC and Puducherry 7 TMC.
The court also directed the Centre to set up the Cauvery Water Management Authority and the Cauvery Water Regulation Committee to implement the award and to monitor releases on a monthly basis.
The authority fixes a monthly schedule of releases that Karnataka must make at Billigundulu, based on the flows expected in a normal year. In a normal monsoon year the system works with relatively little friction.
In a deficit year, however, the monthly schedule becomes a source of friction, because Karnataka says it cannot release the scheduled quantum when its own reservoirs have received less inflow, while Tamil Nadu insists that the schedule must be honoured regardless of the rainfall in the catchment.
That pattern has repeated itself many times since the authority was set up. In 2023, Tamil Nadu moved the Supreme Court seeking the release of 24,000 cubic feet per second of water, and the court eventually declined to interfere with the expert body's assessment.
Similar applications have been filed in other distress years, and the court has generally been reluctant to substitute its own judgment for that of the authority and the regulation committee, which monitor reservoir levels and rainfall data on a weekly basis.
Friday's order follows that approach. By dismissing the applications, the court has left the question of releases to the authority's monthly mechanism rather than ordering an additional release. The decision will come as a disappointment to farmers in Tamil Nadu's delta districts, where the samba crop depends on timely releases.
For Karnataka, the order is a relief, because the state had argued that its reservoirs could not sustain the additional release in a rain-deficient year.
The dispute also has a political dimension in both states. In Tamil Nadu, the Cauvery issue is an emotive subject, and every government in the state is under pressure to be seen as fighting for the state's share of water. In Karnataka, the release of water to Tamil Nadu is equally sensitive, particularly in the Cauvery basin districts of Mandya, Mysuru and Hassan, where farmers argue that their own crops suffer when water is released downstream.
The measuring station at Billigundulu, on the Karnataka-Tamil Nadu border, is central to the dispute. It is the point at which Karnataka's compliance with the release schedule is measured, and disagreements over the flows recorded there often form the basis of the cases that reach the Supreme Court. Tamil Nadu's claim in this case was built around the flows recorded at Billigundulu up to October 6, which the state said showed a shortfall of 11.719 TMC against what was due.
The court's order does not end the underlying dispute. The authority will continue to monitor the situation, and either state can return to the court if it believes the monthly releases are not being made. With the north-east monsoon now under way, the inflows into the Cauvery basin over the coming weeks will determine whether the tension eases or whether the matter returns to the courtroom.
For the moment, the immediate consequence of Friday's order is that Tamil Nadu will have to manage its irrigation needs from the water it is already receiving, and from the storage in its own reservoirs, including the Mettur dam, which is the lifeline of the delta.
Farmers' organisations in the delta have been demanding that the state government press the Centre to ensure the release schedule is followed, and the state government is expected to raise the matter again before the authority at its next meeting.
The case, titled State of Tamil Nadu versus State of Karnataka, has now been decided at the level of the two applications, and the third application for additional documents will also stand dismissed. The longer history of the Cauvery dispute, however, remains unresolved in the practical sense, and every deficit year brings the two states back to the same argument over a river that neither can do without.
(Reporting based on The Times of India and LiveLaw.)